L W Infrastructure v Lim Chin San: Natural Justice in Arbitration & Additional Awards

The Singapore Court of Appeal heard two appeals, CA 17/2012 by L W Infrastructure Pte Ltd (Defendant) and CA 26/2012 by Lim Chin San Contractors Pte Ltd (Plaintiff), arising from a High Court judgment regarding an arbitration. The dispute concerned a sub-contract for a building project where the Plaintiff failed to complete works, leading to termination by the Defendant. The appeals centered on the rules of natural justice in arbitration, specifically concerning additional awards and the extent of court supervision. The Court of Appeal dismissed both appeals, upholding the High Court's decision to set aside the Additional Award but refusing to declare it a nullity.

1. Case Overview

1.1 Court

Court of Appeal

1.2 Outcome

Both appeals dismissed with costs.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore Court of Appeal judgment on natural justice in arbitration, focusing on the requirements for additional awards and court intervention.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
L W Infrastructure Pte LtdAppellant, DefendantCorporationAppeal dismissedLost
Lim Chin San Contractors Pte LtdRespondent, Plaintiff, AppellantCorporationAppeal dismissedLost

3. Judges

Judge NameTitleDelivered Judgment
Chan Sek KeongChief JusticeNo
Andrew Phang Boon LeongJustice of the Court of AppealNo
Sundaresh MenonJustice of the Court of AppealYes

4. Counsels

4. Facts

  1. The Plaintiff was the Defendant’s sub-contractor for a building project.
  2. The Plaintiff failed to complete certain works by the agreed completion date.
  3. The Defendant terminated the sub-contract.
  4. The dispute was referred to arbitration.
  5. The Arbitrator rendered his Final Award on 29 June 2010.
  6. The Arbitrator rendered his Supplementary Award No 2 (Remitted Issues) on 21 September 2011.
  7. The Defendant’s solicitors requested an additional award for “pre-award interest” on 17 October 2011.
  8. The Arbitrator issued the Additional Award on 20 October 2011, without hearing from the Plaintiff.

5. Formal Citations

  1. L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal, Civil Appeals Nos 17 and 26 of 2012, [2012] SGCA 57

6. Timeline

DateEvent
Notice of arbitration served by the Defendant on the Plaintiff.
Arbitrator rendered his Final Award.
Arbitrator rendered his Supplementary Award No 2 (Remitted Issues).
Defendant's solicitors requested an additional award for “pre-award interest”.
Arbitrator issued the Additional Award.
Plaintiff’s solicitors protested the Additional Award.
Arbitrator issued a final reply regarding the Additional Award.
Plaintiff filed an originating summons in the High Court.
Judgment reserved.

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court found a breach of natural justice in connection with the making of the additional award.
    • Category: Substantive
    • Sub-Issues:
      • Failure to provide opportunity to be heard
      • Decision based on matters not submitted or argued
  2. Applicability of Section 43(4) of the Arbitration Act
    • Outcome: The court determined that the arbitrator should have given the Plaintiff the right to be heard on the applicability of s 43(4) of the Act prior to coming to his decision.
    • Category: Procedural
    • Sub-Issues:
      • Omission of claim
      • Tribunal exceeding powers
  3. Court's Supervisory Jurisdiction over Arbitration
    • Outcome: The court held that it does not have the power to declare the Additional Award a nullity.
    • Category: Jurisdictional
    • Sub-Issues:
      • Extent of court intervention
      • Power to declare award a nullity

8. Remedies Sought

  1. Setting aside of Additional Award
  2. Declaration that Additional Award is a nullity

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Construction Disputes
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lim Chin San Contractors Pte Ltd v L W Infrastructure Pte LtdHigh CourtYes[2012] 2 SLR 1040SingaporeThe decision from which these appeals arose.
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte LtdHigh CourtYes[2011] 4 SLR 477SingaporeThe High Court dismissed the Plaintiff’s appeal and substantially allowed the Defendant’s appeal and the Final Award was remitted to the Arbitrator for his reconsideration and final disposal.
Mitsui Engineering & Shipbuilding Co Ltd v Easton Graham Rush and anotherCourt of AppealYes[2004] 2 SLR(R) 14SingaporeCited for the principle that courts should only intervene in situations expressly regulated by the Act.
Denmark Skibstekniske Konsulenter A/S I Likvidation (formerly known as Knud E Hansen A/S) v Ultrapolis 3000 Investments Ltd (formerly known as Ultrapolis 3000 Theme Park Investments Ltd)High CourtYes[2010] 3 SLR 661SingaporeCited to show that s 48(1)(a)(v) of the Act would have afforded the defendant an appropriate avenue for seeking recourse if the tribunal was functus officio.
PT Asuransi Jasa Indonesia (Persero) v Dexia Bank SACourt of AppealYes[2007] 1 SLR(R) 597SingaporeCited to support the contention that there may well be occasion for the Court to find that something which purports to be an award is in fact and in substance not an award at all.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeEstablishes the test for challenging an arbitration award as having contravened the rules of natural justice.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 2002 Rev Ed)Singapore
Arbitration Act, s 43(4)Singapore
Arbitration Act, s 48(1)(a)(vii)Singapore
Arbitration Act, s 47Singapore
Arbitration Act, s 48(1)(a)(v)Singapore
Arbitration Act, s 22Singapore
Arbitration Act, s 44Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Natural Justice
  • Additional Award
  • Pre-award Interest
  • Functus Officio
  • Audi Alteram Partem
  • Omission of Claim
  • Arbitral Procedure
  • Supervisory Jurisdiction
  • Actual Prejudice

15.2 Keywords

  • Arbitration
  • Natural Justice
  • Additional Award
  • Singapore
  • Construction Dispute

17. Areas of Law

16. Subjects

  • Arbitration
  • Civil Procedure
  • Contract Law